| Project Name. |
400 MW COMBINE CYCLE POWER PLANT (UNIT 13, 14 & 15) |
| Location. |
Kot Addu, Pakistan |
| Client |
Wapda |
| |
|
|
 |
Design and construction of gas turbine house |
 |
Control room building |
 |
Steam Turbine Plants |
 |
Water treatment plant |
 |
Ancillary structures |
 |
Water intake structure |
 |
Fabrication and erection of steel structure |
 |
Fabrication and erection and testing of CW Pipeline from intake to the Plant. |
 |
Drainage and sewerage system of plant |
 |
Asphalt roads and concrete pavements |
 |
Construction of switchyard pavements |
 |
Construction of Switchyard foundation |
 |
Total concrete batched and placed = 100,000M3 |
 |
Steel structure fabricated and erected = 3000 tons |
|
| |
|
|
|
|
|
|
|
| |
 |
| |
| |
|
 |
 |
 |
400 MW COMBINE CYCLE POWER PLANT (UNIT 13, 14 & 15)
Kot Addu, Pakistan
Client: Wapda |
 |
|
 |
| |
|
|
 |
 |
 |
2X362 MW OIL FIRED AES POWER PLANT
Lalpir, Pakistan
Client: AES |
 |
|
 |
| |
|
|
 |
 |
 |
412MW Combined cycle rousch power plant
Abdul-Hakeem, Pakistan
Client: Rousch Power |
 |
|
 |
| |
|
|
 |
 |
 |
125 MW OIL FIRED SABA POWER PLANT
Farooqabad, District Sheikhupura - Pakistan
Client: Costal Power Pvt. Ltd |
 |
|
 |
| |
|
|
 |
 |
 |
300 MW THERMAL POWER PLANT
Guddu, Pakistan
Client: WAPDA |
 |
|
 |
| |
|
|
 |
 |
 |
225 MW COMBINE CYCLE POWER PLANT
Balloki , Pakistan
Client: Orient Power |
 |
|
 |
| |
|
|
 |
 |
 |
132/11.5 KV GAS INSULATION SWITCHGEAR SUBSTATION
Lahore
Client: Wapda |
 |
|
 |
| |
|
|
|
|
|
|
|